Data Center Relocation Update

Delays in the bid process for the renovation of the former Repro Graphics building have pushed the relocation of Data Center equipment from Hutchison Hall to the new building further into the fall. The latest schedule established by Architects and Engineers indicates that the renovated facility will be ready for occupancy by mid-November. The first systems should be moved into the facility in late November, and the relocation completed by March 1999. A firmer schedule will be published when the bid process is completed in late August. For more information on the Data Center relocation, visit the Data Center Web site at http://ir.ucdavis.edu/dc/.